Hankinson 6″ Transmission Pipeline Reroute
ECI Contracting rerouted approximately 3,400 feet of 6″ steel natural gas transmission pipeline near Hankinson, North Dakota, for a regional natural gas utility. Driven by a railroad track expansion, the project included new pipeline installation, an HDD crossing, stopping and tapping, purging, and retirement of the existing line, all completed in house, on time, and on budget within a tight window set by downstream customers.

Project Details
- Location: Hankinson, ND
- Client: Regional natural gas utility
- ~3,400 linear feet of 6″ steel transmission pipeline
- One HDD crossing
- Stopping/tapping, purging, and retirement of the existing line
- Completion date: September 28, 2026
An existing 6″ transmission line near Hankinson, ND, runs parallel to a railroad track until it reaches its final delivery point at Hankinson Renewables. A planned expansion of the track required the pipeline to be moved. The utility engaged ECI to reroute approximately 3,400 feet of the line and complete the work within a short window set by downstream customers, minimizing impact to their business.
ECI Scope
The project presented several challenges:
- Short turnaround driven by the downstream customers’ schedule
- Equipment and manpower logistics to support a compressed timeline
- Material testing requirements, including hydrostatic pressure testing and Non-Destructive Examination (NDE)
- A restricted work area alongside active railroad tracks with ongoing construction

Technical Solution
- Pipeline installation of ~3,400 feet of 6″ steel, including trenching, welding, field coating, and lowering-in
- One HDD crossing, with added oversight during pullback to protect pipe coating and ensure proper installation
- Stopping and tapping to tie in the new line while keeping the system in service
- Purging and retirement of the abandoned section of the existing line
- Qualified welders working to approved company welding procedures, with NDE completed and accepted before coating
- Holiday testing and coating repair before lowering-in and backfill
- Hydrostatic testing, cleaning, and drying completed before final tie-in

Project Execution
- Safety took precedence over schedule and production, with daily planning and tailgate meetings before work began and stop-work authority for every person on site
- Close communication with the client’s Construction Services team before critical activities, including welding, NDE, coating, lowering-in, HDD operations, pressure testing, and tie-ins
- Pipe and fittings inspected on delivery, with factory coatings protected and material traceability (heat numbers) maintained
- Excavations sized for safe welding, inspection, and coating, with trench conditions and groundwater managed before lowering-in
- Full documentation package, including as-builts (AFC redlines), HDD bore records, pressure test records, equipment calibration records, JSAs, and operator qualifications

Result
ECI completed the reroute on time and on budget, with all work performed in house and no unplanned customer interruptions. The new line was installed, tested, and tied in within the window set by downstream customers, clearing the way for the railroad track expansion.
Highlights
- Completed on time and on budget
- All work self-performed by ECI crews
- Zero unplanned customer interruptions
- Safe execution in a restricted work zone next to active rail and ongoing construction
- Pipeline installation, HDD, stopping/tapping, purging, and line retirement under one contractor
ECI Project Team
- Tom Burmiester, Supervisor
- Landon Duncan, General Superintendent
- Kelly Klingelhoets, Foreman